1. Prepare Substrate
2. Check Environment
3. Read Surface Temp.
4. Measure Dew Point
5. Pre-weigh CC Test
6. Clean the Slab
7. Open Lid & Set Dish
8. Install the Dome
9. Use the Press!
10. Place the Cone
11. Recover Dish Unit
12. Re-weigh / Calculate
13. Conduct pH Tests
14. For procedures using meters and other test devices, please refer to manufacturer's pages which are linked to each product page.